比利时鲁汶大学(KU Leuven)大学Leus教授学术报告通知

来源: | 发布时间:2016-05-23| 点击:

【报告题目】A model for scheduling with activity failures

【报告人】Roel Leus博士,比利时鲁汶大学bat365在线平台官网教授,运筹学与商业统计研究中心主任

【会议主持】周泓 教授

【报告时间】2016523日(周一)下午15:00-17:00

【报告地点】北航新主楼A座618室

Title: A model for scheduling with activity failures

Abstract: An R&D project typically consists of several stages. Due to technological risks, the project may have to be terminated before completion, each stage having a specific likelihood of success. In the project planning and scheduling literature, this technological uncertainty has typically been ignored and project plans are developed only for scenarios in which the project succeeds. In this work we examine how to schedule projects in order to maximize their expected net present value when the project activities have a probability of failure and when an activity’s failure leads to overall project termination. We describe a general model, develop an exact algorithm and establish a link with stochastic scheduling.